Zero Waste commission backs $2.1M recycling data contract; closed FM 812 landfill to host city’s largest solar site

The Zero Waste Advisory Commission unanimously recommended a contract of up to $2.1 million with RRS to measure Austin’s progress toward zero waste, and heard that the closed FM 812 landfill will host a 58-acre Austin Energy solar array.

Share this storyXFacebookLinkedIn

Aerial map of the closed FM 812 landfill outlined in red between FM 812, FM 973 and Moores Bridge Road

Austin can’t easily tell how close it is to its goal of keeping 90% of discarded material out of landfills, because private haulers collect most of the city’s trash and recycling. On Oct. 14, the Zero Waste Advisory Commission unanimously recommended a contract of up to $2.1 million to measure that progress regularly. Commissioners also got a history of the city’s closed FM 812 landfill near the airport. Staff said a 58-acre Austin Energy solar array planned there would be the largest single-site solar installation the city owns.

The rate studies. The contract with Resource Recycling Systems Inc., known as RRS, would run three years with up to three one-year extensions, according to the draft request for council action. Austin Resource Recovery staff told commissioners the department has budgeted about $350,000 a year but may spend less, according to the meeting video. Staff described three kinds of studies:

  • Per capita disposal: how much each resident throws away each year.
  • Diversion rate: how much material is kept out of landfills, the measure behind the city’s 90% goal.
  • Capture rate: whether materials such as aluminum and cardboard end up in the right bin, which staff said could guide targeted outreach campaigns.

Staff said the city collects only about 15% to 25% of the community’s material, and private haulers collect the rest. They said past community-wide studies happened only every several years, around 2015 and again around 2020 or 2021. The new studies would cover residential and commercial single-stream material but not construction and demolition debris. Staff said the solicitation was published in April and closed in June, and that the yearly cost is in line with the roughly $300,000 the last community-wide study cost.

The FM 812 landfill. Deputy Director Gena McKinley’s presentation described the roughly 391-acre site in Travis County near Austin-Bergstrom International Airport, which took waste from the 1960s to 2009. In 1995, state regulators approved converting it to a Type IV site that accepts only construction, demolition and land-clearing debris. Household-waste operations ended in 1999. McKinley told commissioners the change was made because of the landfill’s proximity to the airport’s airspace. She said the site has been in post-closure since May 2021. Current uses include:

  • Austin Energy laydown yard: an equipment and vehicle yard McKinley said is expanding to 10 acres off FM 973.
  • Solar array: 58.224 acres, with UPower selected as the vendor for Austin Energy. McKinley said it should be running by 2028.
  • Leachate line: McKinley said the project will connect the landfill’s leachate line directly to the city’s system so the liquid no longer has to be pumped and hauled away. The slides give a 180-day construction schedule.
  • Cart operations: the department stores and deploys residential carts and litter containers from the site, she said.

Asked how much of the site could be available if the city returned to accepting construction and demolition debris, McKinley said she would get back to the commission, according to the video.

Other business. In her monthly operations update, McKinley said the department executed agreements with its two residential recycling processors for the final term of their contracts and plans to brief commissioners on the terms. The city, Travis County and local nonprofits are holding a food rescue mini summit for businesses Oct. 19. The annual reporting period under the Universal Recycling Ordinance opened Oct. 1 and runs to Feb. 1. Commissioners said a construction and demolition debris proposal likely won’t be ready until about January.

What’s next. The RRS contract is Item 30 on the City Council’s Oct. 22 final agenda.