The public-private partnership building Waterloo Greenway along Waller Creek downtown will present its yearly project plan on Wednesday, Oct. 21. The report shows where taxpayer money has gone on the newly opened Confluence and what comes next: final plans for Sir Swante Palm Park and a long-awaited stretch of creek and trail between Fourth and 12th streets.
The meeting. The Waller Creek Local Government Corporation board meets at 1:30 p.m. in the City Council Chamber at City Hall, 301 W. Second St., according to the agenda. The corporation was set up by the city to oversee the greenway work. The City of Austin and the nonprofit Waterloo Greenway Conservancy carry out the projects under that oversight. The board is set to vote to approve the presentation of the 2026 Annual Project Plan Report (an amended version was posted ahead of the meeting). Public comment is allowed in person or by phone. Remote speakers must register by noon Tuesday, Oct. 20, with board liaison Thomas Grauzer at (512) 552-6837 or Thomas.grauzer@austintexas.gov.
Where the greenway stands. The full vision calls for 35 acres of public green space along 1.5 miles of restored creek from Waterloo Park to Lady Bird Lake, with 3 miles of new hike-and-bike trails, according to the report.
- Phase 1. Waterloo Park, 11 acres at the north end, opened in 2021. The report says it has drawn more than 1.4 million visitors. Symphony Square is also complete.
- The Confluence. This 13-acre stretch between Fourth Street and Lady Bird Lake opened June 6. It includes three 140-foot lattice bridges near the Ann and Roy Butler Hike-and-Bike Trail, about 200,000 plants and more than 1,500 trees, and a biofiltration pond that treats runoff from 26 acres of downtown. The construction budget is $84.4 million, and about $73.5 million had been spent, leaving $10.9 million, or 13%. The city put in $60.5 million (72%), most of it, $50.3 million, from Watershed Protection. The conservancy contributed $12.5 million (15%) and the U.S. Army Corps of Engineers $11.4 million (13%). The prime contractor was Jay-Reese Contractors.
- Sir Swante Palm Park. Design of the park, including restoration of its historic Shelter House, is nearly finished at a cost of $775,066, split evenly between the 2012 parks bond and the conservancy. The next step, construction documents, permitting and bidding, is estimated at $1.85 million and is expected to come to the board in the first quarter of 2027. The report’s map shows construction beginning in 2027.
- Fourth to 12th streets. Schematic design, budgeted at $3.6 million, is awaiting its final invoice. A $4.26 million design development phase began Aug. 12 and is expected to wrap up in the second quarter of 2027. It is funded by $2.7 million from the downtown tax increment financing zone through Watershed Protection, $1.08 million from the Corps and $488,230 from a federal EPA community grant. The budget for final construction documents and bidding hasn’t been set; that plan is expected to reach the board in the third quarter of 2027. The report says the work may cover all eight blocks or only part of them.
The report says the more detailed design is meant to cut costs and make the Fourth-to-12th stretch “shovel ready” for new local and federal funding. A separate coordination contract with nearby developments has a $460,000 budget, with about $156,000 left.
Who’s on the board. Eric Johnson is president, Martha Smiley vice president, Rudy Green secretary and Ann Eaton treasurer. The other directors are Jesús Aguirre, Andrea Bates, Tim LaFrey, Jorge Morales, Allan Shearer and Melba Whatley, according to the agenda. Aguirre is the city’s parks director and previously served as CEO of Waterloo Greenway, the conservancy that is the city’s partner on the project, according to the city. Meeting records are on the board’s page.