Students moved into the new Pecan Springs Elementary in August. Austin ISD holds the official grand opening Thursday.
The ceremony runs from 2:30 to 3:30 p.m. Thursday, Nov. 19, at the school, 3210 Rogge Lane in Northeast Austin, according to the district’s event listing. The district asks guests to RSVP online. The form says to park in the lot off Reicher Drive, with overflow parking at Sacred Heart Catholic Church, 5909 Reicher Drive.
What voters paid for. Pecan Springs was a full modernization in the $2.44 billion 2022 bond. The district tore down the school, which opened in 1957, and built a new one on the same site. The total project budget is $47,657,000, according to the district’s bond page. That figure covers construction plus fees and materials.
A state accessibility filing lists an estimated construction cost of $44.8 million for a 77,300-square-foot building, with work scheduled from Jan. 6, 2025, to May 29, 2026.
The new campus is built for about 375 students, according to the district’s project FAQ. It has flexible classrooms, outdoor learning areas, spaces for teachers to work together and a secure entry vestibule. O’Connell Robertson designed it, Vaughn Construction built it and AECOM manages the bond program.
During construction, Pecan Springs students went to class in portable buildings at Winn Montessori, 3500 Susquehanna Lane, with district buses from neighborhood stops.
Still on the punch list. The bond page’s fourth-quarter update says Vaughn is still doing warranty work and finishing punch-list items, and has started right-of-way work outside the school. It also says the district plans to replace the kitchen flooring and the walk-in cooler in summer 2027. That’s unusual for a building that opened three months ago, and the update doesn’t say why. The Dispatch has not confirmed the reason or who will pay for the work.
Part of a long list. When Pecan Springs broke ground in December 2024, it was the 12th of 25 modernization or renovation groundbreakings in the 2022 bond, Community Impact reported. The district expects the last of those schools to open in 2028.
At that groundbreaking, Superintendent Matias Segura framed the rebuild as part of the district’s effort to address historical inequities in underserved neighborhoods. In 2023 district data, the school’s students were about 63% Hispanic and 28% Black, Community Impact reported.
Families with questions about the event can use the questions-and-comments form on the bond program website, the RSVP form says.