Austin wants you to watch where your bond money goes. Now there’s something to watch it with.
Capital Delivery Services launched the Austin Bond Dashboard on Oct. 1. The release calls it a “transparent, community-friendly view” of projects paid for by the city’s 2016, 2018, 2020 and 2022 general obligation bonds. The dashboard itself, also linked from AustinTexas.gov/CapitalDelivery, is an Esri ArcGIS app. Its numbers come from two public city data layers, which Dispatch queried directly on Monday morning: project records and proposition finances. The finance layer was last refreshed Oct. 4.
The money. Across 10 propositions, voters authorized $2.455 billion: $720 million in 2016, $925 million in 2018, $460 million in 2020 and $350 million in 2022. The city reports about $1.955 billion obligated and about $1.715 billion spent, which leaves roughly $740 million not yet out the door. The older bonds are furthest along. About 85% of the 2018 money is spent, compared with 73% for 2016, 61% for 2020 and 35% for the 2022 affordable housing bond.
The projects. The data holds 1,284 project records. Dispatch sorted them using the dashboard’s own status filters:
- 770 completed
- 141 in construction
- 136 in design
- 170 “anticipated”
- 63 cancelled
- 4 active projects in phases the filters don’t catch
The “anticipated” figure needs a footnote. According to the dashboard’s configuration, it includes 43 projects the city’s data marks as on hold. Those projects are shown alongside ones that simply haven’t started yet.
The cancellations. The city says a cancelled project is one that “will not move forward as originally planned, and its funds have been or are being reassigned.” The release adds a caveat worth framing: “A cancellation does not necessarily mean the community need has been resolved.”
The 63 cancelled records carry about $21.9 million in appropriations. Most of that, about $21.1 million, is booked as already spent. Forty-six of them are transportation projects and nine are affordable housing deals.
The biggest by far is the Redbud Trail Bridge over Lady Bird Lake, a 2018 Prop G record showing $12.3 million appropriated and $11.8 million spent. The bridge itself isn’t dead. The city’s project page says the project is still in design. It was first planned as a full replacement and now focuses on rehabilitating parts of the existing structure. “Cancelled” may describe the original plan, not the bridge. Dispatch hasn’t confirmed that with the city.
The release doesn’t say who decides where reassigned money goes, whether that comes back to council, or whether cancelled needs get revisited.
Why now. The dashboard went live as Austin heads into a Nov. 3 election on two new bonds: $260 million for parks and $35 million for libraries (bond notice). Council put both on the ballot in August. Before that unanimous final vote, Mayor Kirk Watson and two council members opposed calling the election, arguing that too much previously approved bond money was still unspent, according to the Austin Current. Early voting starts Oct. 19.
Mapping is coming next, the city says. Until then, the spreadsheet-brained finally have a public ledger to argue over.