Airport commission backs $224M utility contract increase a day after terminal power outage

A day after a partial power outage at Austin-Bergstrom, the Airport Advisory Commission unanimously backed a $224 million increase to the airport’s utility infrastructure contract, which staff said adds redundant power lines. Council votes Oct. 22.

Share this storyXFacebookLinkedIn

Austin airport slide for the Utility Infrastructure Campus-Wide project showing an aerial of drainage basins and an electrical equipment enclosure, with designer HDR and contractor Sundt/Archer Western

A partial power outage at Austin-Bergstrom International Airport delayed flights the evening of Oct. 13. The next afternoon, airport staff told the Airport Advisory Commission that a $224 million expansion of the airport’s underground utility contract would add backup power lines the terminal doesn’t have now. The commission voted unanimously Oct. 14 to recommend the increase, which would bring the Sundt/Archer Western contract for the Utility Infrastructure Campus-Wide project to $344 million. The City Council is scheduled to vote on it Oct. 22.

Why the contract grew. Airport Development Officer Rustin Roussel told commissioners the utility project was scoped early in the airport expansion program, when plans called for a 20-gate concourse and a smaller arrivals and departures hall, according to the meeting video. He said the plans have since grown by several gates, plus the six-gate Concourse M. That means more stormwater drainage and detention capacity and heavier electrical loads, he said. The airport decided to switch to a medium-voltage primary power system. Roussel said that roughly doubles the duct banks and cable the contractor must install. He also cited rising costs for electrical materials and labor as large construction projects compete for electricians.

The outage. Commissioner Mike Trimble asked whether the work would make power at the airport more reliable, citing the previous day’s outage. Roussel said the new design runs redundant duct banks separately, so that if one line is damaged there’s a backup path. He said that kind of redundancy isn’t available today and that how much it would help in any one event depends on where the damage is, according to the video. The Oct. 13 outage began about 5:18 p.m. and hit parts of the Barbara Jordan Terminal, including ticket counters. It delayed arriving and departing flights, CBS Austin reported. The airport said power was fully restored by 8:10 p.m., and officials didn’t identify a cause, The Austin Focal reported.

Commissioners’ questions. Members asked whether this would be the last increase and how it would be paid for:

  • A ceiling. Roussel said the airport expects $344 million to be the ceiling for this project. He said guaranteed maximum prices are being negotiated, and other projects are far enough along in design that staff hope not to return for more.
  • Contingency. The contract is a construction-manager-at-risk agreement. Roussel said the contractor carries its own contingency, and the airport program carries contingency separately.
  • Federal grants. He said about $25 million in federal grants covers stormwater work in the project’s first phase and isn’t part of the $224 million increase.
  • Funding. Staff said the increase is paid from airport capital funds under the current bond program. The agenda item says the money is in Austin Aviation’s capital budget.
  • Timing. The project’s ceremonial groundbreaking is set for Monday, Oct. 19, three days before the Council vote, according to the project update slides. Roussel said work under the existing contract is under way, but construction on the expanded pieces won’t start without approval.

Airport finances and flights. In the August financial report, Deputy Chief Financial Officer Anupa Gharpurey said fiscal-year-to-date passenger boardings were up 4.3% and total revenues were up about $84 million, or 26%, while expenses came in under budget. Cargo fell 3.7% for the month and 2.7% for the year. Commissioner Clifford Chiu asked staff to regularly report debt-service coverage, days of cash on hand and cost per boarding passenger as the airport takes on expansion debt, and staff said they track those measures. Air service staff said seat capacity is up 2.7% in the fourth quarter and nearly 5% for early 2027. They cited new Southwest routes including Portland, Ore.; Liberia, Costa Rica; and Nassau, Bahamas, plus 36 extra scheduled flights for Formula 1 race weekend.

Other business. The commission unanimously recommended a $846,219 increase to a NetBrain network-management software contract shared by Austin Energy and the aviation department. That item is Council Item 24. The commission also adopted its 2027 meeting calendar. Staff said the Atrium Infill project opened this month and that the Concourse M and midfield maintenance ramp groundbreaking took place.

What’s next. The Sundt/Archer Western amendment is Item 27 on the Council’s Oct. 22 final agenda. The commission’s next regular meeting is Nov. 18, the chair said.