Barton Springs Road’s century-old bridge gets an open house Nov. 16, and its construction start has slipped to late 2028

The city will show plans for the bridge replacement at Zilker Park’s front door Monday, Nov. 16, 5-7 p.m., at the Dougherty Arts Center. Construction is now projected for late 2028, not summer 2027.

Share this storyXFacebookLinkedIn

Concrete open-spandrel arches and piers of the Barton Springs Road bridge seen from below, over the green water of Barton Creek

The bridge that carries Barton Springs Road over Barton Creek, the front door to Zilker Park, is about 100 years old. The city wants to replace it, and now you can see what’s coming.

Austin Transportation and Public Works announced in its Nov. 2 Mobility News that it will hold a community open house on Monday, Nov. 16, 2026, from 5 to 7 p.m. at the Dougherty Arts Center, 1110 Barton Springs Road. People can drop in at any time to look at the latest plans and ask questions. Staff from TxDOT, Transportation and Public Works and Capital Delivery Services will be there, according to the city’s release.

The project page on SpeakUp Austin says this open house is not the formal public hearing required by the National Environmental Policy Act. Details on that hearing and a comment period will come later.

The schedule moved. The SpeakUp page now projects a federal environmental decision in late 2027 and the start of construction in late 2028. As recently as June, the city’s earlier project page listed “Construction: Beginning summer 2027,” according to an archived copy. That page now returns an error. The new timeline also includes parkland hearings under Chapter 26 of the Texas Parks and Wildlife Code, currently targeted for August through October 2027, because the project would use dedicated parkland. The city says those dates aren’t confirmed.

What’s planned. The current design calls for:

  • Two travel lanes in each direction, separated by a raised median
  • A 12-foot two-way bike lane on each side behind concrete barriers
  • Wider sidewalks: about 13.5 feet on the north side and 17.5 feet on the south
  • Wider trails under the bridge and stabilized creek banks
  • More room and structural support for the Zilker Eagle mini train
  • Design elements meant to recall the original arches
  • Changes at the Barton Springs Road and Azie Morton Road intersection

The new bridge would be about 109 feet wide. It would also do away with the existing bridge’s load posting, the weight limit the old structure carries now.

The lane count may draw attention. In August 2023, the city’s Barton Springs Road safety project cut westbound traffic on the bridge to one lane and added protected bike lanes, according to the archived project page. The replacement design brings back two lanes in each direction and keeps separated bike lanes.

Why replace it. The city says a detailed inspection found deterioration in the deck, floor beams, columns and arches. The project team estimated that a rehabilitation would cost about as much as a new bridge but add only up to 50 more years of life, while a new bridge would last at least 100 years. On Dec. 14, 2023, City Council approved the replacement option 9-0, with Council Member Alison Alter off the dais and Council Member Ryan Alter absent, according to council records.

The money. The U.S. Department of Transportation awarded the city a $32 million Bridge Investment Program grant on Oct. 31, 2024. Council voted to accept it on April 24, 2025. The grant requires an $8 million local match from mobility bond money, for a total project cost of up to $40 million, according to that council item and the Federal Highway Administration’s award fact sheet. The federal fact sheet counts about 11,275 vehicles a day on the bridge. The SpeakUp page says more funding is expected from the 2020 Mobility Bond. Those cost figures predate the new 2028 construction start.

A little history. San Antonio engineer Terrell Bartlett designed the original three-arch, open-spandrel concrete bridge. Construction started in November 1925, and the bridge opened to traffic on June 21, 1926, after rain pushed back the planned June 18 opening. It cost $28,819.05. Those details come from a draft historic narrative in city records, which cites newspaper coverage from the time. Crews widened it to 48 feet in 1946. The bridge isn’t a designated landmark on its own, but it is a contributing resource in the Zilker Park Historic District, which is listed on the National Register of Historic Places. That’s one reason the federal review includes historic resources.

The city says construction will bring temporary traffic and park-access impacts, but phasing is still being worked out. Questions can go to MobilityBonds@AustinTexas.gov or 512-974-2300.