Austin City Council will decide Nov. 19 whether to accept $25 million from the Texas Department of Transportation to build a new Butler Trail boardwalk on Lady Bird Lake.
The boardwalk would run along the south shore between South First Street and South Congress Avenue, in front of the Hyatt Regency, where the trail narrows. TxDOT is offering the money as mitigation for its I-35 Capital Express Central project, and no city match is required. But the city’s own backup for Item 52 says Austin would be responsible for 100% of any cost above $25 million, plus right-of-way, utility relocation and long-term maintenance. If the project comes in under budget, the leftover money goes back to TxDOT.
The trail draws about 5 million visits a year, according to the city’s recommendation for action, which calls it Austin’s most popular trail. The project would build a 14-foot-wide trail with 2-foot shoulders, stabilize eroding cliffs and add a boardwalk over the water. A companion item, Item 11, would hand up to $25 million to the Austin Public Facilities Corporation, a city-created entity, to design and build it.
The short version: The boardwalk has been promised since 2023, when TxDOT added it to the I-35 environmental decision. It is a fixed-price state gift with an open-ended city tail. Council is being asked to sign up for that tail without an engineering estimate, a design or the funding agreement itself in the posted backup.
Why TxDOT is paying. The I-35 project permanently takes about 0.8 acres of city parkland and temporarily occupies about 2.5 acres, according to a Feb. 5, 2026, letter from TxDOT Austin District Engineer Tucker Ferguson to Mayor . The letter is attached to a June 2 memo to Council from Parks Director Jesús Aguirre. Federal rules required TxDOT to compensate the city for that land, and it did: about $17.6 million, which Council made available through a Feb. 5, 2026, action, the memo says. The $25 million boardwalk is separate. TxDOT calls it mitigation “outside of federal requirements.”
Ferguson’s letter also makes clear the money cannot be redirected. The boardwalk “is specifically named in the Record of Decision (ROD) and cannot be replaced with another project,” he wrote. “If the city elects to not sign the AFA for the boardwalk with TxDOT, the mitigation will be removed from the FEIS/ROD through an environmental re-evaluation.” The AFA is the advance funding agreement Council would authorize; the FEIS/ROD is TxDOT’s final environmental decision for I-35.
The overrun clause. The recommendation for action spells out the deal. TxDOT’s contribution is a “$25,000,000 maximum fixed state contribution.” The city’s estimated share is $0 “provided there are no utility relocations, right-of-way, easement, or real property acquisition costs, and total project costs remain at or below $25,000,000.” The city also takes on environmental review, construction management and “100 percent of any cost overruns exceeding the $25 million state limit.”
Long-term upkeep would fall to Austin Transportation and Public Works, which maintains the existing boardwalk on the lake’s southeast side. The Trail Conservancy, the nonprofit that partners with the city on the Butler Trail, would handle operations, general maintenance and programming, according to the capital budget fiscal note. Neither document estimates what that maintenance will cost.
Who builds it. In March 2023, Council created the Austin Public Facilities Corporation to help finance, build and place public facilities in service, according to the Item 11 backup. Its board recommended the boardwalk project June 15, 2026. Under Item 11, the corporation would handle predevelopment, design and construction. The corporation’s role is the latest turn in a yearslong dispute over who controls the money.
KUT reported in March, based on emails obtained under the Texas Public Information Act, that TxDOT’s Austin district and the Trail Conservancy spent more than two years trying to route the $25 million to the nonprofit without a Council vote. KUT also reported that a senior parks official wrote internally in January 2025 that the parks department did not see a need for the boardwalk, and that parks staff asked TxDOT to redirect the money to other parks projects. East Austin community leaders told KUT the boardwalk plan overlooks needs east of I-35.
The document against the announcement. The same recommendation for action that lists the city’s overrun duty also says, “The City will not be required to contribute additional funds beyond those currently budgeted to this project. The project will be designed to the available budget, and no additional funds will be needed.” Those two statements can both hold only if the design fits under $25 million and no right-of-way or utility costs turn up. The backup shows the project in the “Preliminary” phase, with no engineering estimate attached.
The funding agreement itself is not in the posted backup. Item 52’s attachments are a two-page draft ordinance, the fiscal note and the recommendation for action, so Council’s summary of the terms is the only public version. Aguirre told a public meeting in March 2025 that he had hoped to avoid an overrun arrangement so the department wouldn’t take capital dollars from elsewhere, KUT reported.
For comparison: The existing Lady Bird Lake boardwalk, which opened in 2014, was a $28 million project mostly funded with city property taxes, according to KUT.
What’s unresolved. The backup does not say how long the new segment is or when it would be built, and its only cost figure is a “total estimated project cost” of $25 million, the same as TxDOT’s cap. It also does not say whether an earlier offer still stands: the Trail Conservancy told KUT in March that if it managed the project and costs topped $25 million, the nonprofit, not the city, would raise the added money. Under Item 11, the public facilities corporation would manage construction instead. Austin Parks and Recreation and Austin Financial Services, both listed as contacts on the items, could answer.
What happens next. Council convenes Thursday, Nov. 19, at 10 a.m. at Austin City Hall, 301 W. Second St. The posted agenda is a draft and can change. Backup documents are linked from the city’s Nov. 19 meeting page. Speaker registration opens Monday, Nov. 16, at 10 a.m., according to the city’s Council Meeting Information Center, which also links to ATXN video of meetings. If Council approves, TxDOT would first release money for engineering, then the construction money once design reaches the 90% milestone, according to the recommendation for action.