Austin plans to start rebuilding East 51st Street from Cameron Road to Berkman Drive, between Mueller and Windsor Park, in late 2027. The design keeps two car lanes in each direction and adds protected bike lanes and a signalized protected intersection at Berkman Drive. Residents who want one lane each way and roundabouts made their case to the City Council’s Mobility Committee on Oct. 1. Staff said changing course now would add years and costs.
The committee heard the update on the East 51st Street project, a 2012 bond project, at its Oct. 1 meeting. It also heard briefings on electric air taxis and on equitable transit-oriented development, and the mobility director’s monthly report.
Chair Paige Ellis, Vice Chair Zohaib “Zo” Qadri, Mayor Pro Tem José “Chito” Vela and Council Member Krista Laine were all present, according to the agenda and the city’s meeting transcript.
What the city plans for 51st Street
Transportation and Public Works Director Richard Mendoza said the corridor’s 2012 vision plan, drawn up as Mueller was being redeveloped, called for a street that calms traffic and connects Windsor Park, Mueller and nearby parks. Voters approved partial construction money in the 2012 bond. Preliminary engineering was done in 2015 and design began in 2017. Mendoza said the project was slowed by new Atlas 14 floodplain rules that forced a redesign and by problems with a design consultant. The city brought in a new consultant in late 2024.
The staff presentation lists what the current design includes:
- full-depth road reconstruction with raised medians;
- new CapMetro bus stops;
- separated bike and pedestrian paths;
- a protected intersection at Berkman Drive;
- upgraded signals, trees, and water and wastewater lines; and
- a new storm drain system.
Mendoza said a 2012 study and the current consultant both found the Berkman intersection would need a two-lane roundabout. That would require buying land from at least four parcels, affect parkland and business access, move Austin Energy power lines and add impervious cover that would trigger major drainage work. He said condemnation alone could add at least two years. The presentation’s alternative schedule shows construction pushed to 2031–2033 if the intersections were redesigned.
Assistant Director Anna Martin said 60 to 70 people came to a June open house. After that feedback, staff straightened the bike and pedestrian paths through the Berkman intersection. The project will lay underground conduit for a future traffic signal at Lancaster Boulevard. A pedestrian hybrid beacon at Tilly Street, just outside the project, has separate funding, Martin said.
Mendoza said the project is on track for a final permit resubmittal in early 2027, a construction bid early next year and construction starting in late 2027. He said construction would take about two years.
The case for a road diet
Three public speakers opposed the design. A Mueller resident who said she is a transportation engineer argued the plan does not follow the Austin Strategic Mobility Plan or Vision Zero practices. She said every intersection should be a one-lane roundabout, with one car lane in each direction. Adam Greenfield of Safe Streets Austin said about 20 local businesses and organizations support a slower, narrower street. A Windsor Park resident who serves on a city commission said four lanes of traffic would not deliver the main-street feel the vision plan described.
Qadri, who said he lives in the Mueller neighborhood, cited Safe Streets figures. Barton Springs Road carried just over 24,000 vehicles a day before the city cut it from four lanes to two. East 51st Street carried just under 25,000 in 2025. He asked why the same change could not work on 51st Street. Martin said traffic in the area has approached 30,000 to 35,000 vehicles a day, and the highest volumes the city has handled in past four-to-two conversions were in the 20,000 to 25,000 range. Staff said lane conversions are not one-size-fits-all. They said the Barton Springs change was a pilot after a serious crash, while 51st Street is a long-term capital project that can fit protected bike lanes and sidewalks on both sides.
Staff said similar intersection projects under the city’s Vision Zero program have seen a 30% to 37% drop in deaths and serious injuries. Asked by Qadri why the project took so long, Mendoza said the city funded construction in 2012 without a fully developed preliminary engineering report. He said the city has since learned from that. Assistant City Manager Mike Rogers said city staff acknowledge mistakes on 2012 bond projects. He said the city has changed how it scopes and delivers them.
One committee member, who cited past road diets on Cameron Road and North Loop Boulevard, said redesign could raise costs and leave the project unfunded; Mendoza said the budget is already tight. The member said Windsor Park residents worry traffic would cut through neighborhood streets if 51st loses lanes, and noted that a vacant block between Cameron Road and Lancaster is expected to hold about 1,500 homes. The member asked staff for a memo explaining the lane decision for council and the public. Laine asked what the project might add if money were not so tight. Staff said the design meets the city’s Transportation Criteria Manual and that nothing needed for the corridor’s goals had been cut.
Air taxis and other items
Rogers, Transportation and Public Works Assistant Director Lewis Leff and ATCEMS Division Chief Christopher Lester briefed the committee on electric vertical takeoff and landing aircraft, or eVTOLs. The FAA announced its eVTOL Integration Pilot Program in March 2026, according to the presentation. TxDOT’s Project Nexus is part of it. Leff said an application involving Austin-based LIFT Aircraft was not selected. The city is still working with the company. Lester said ATCEMS has talked with LIFT for years about flying paramedics to some calls to get past traffic. Qadri raised safety and regulation questions. Laine asked how air rights and the land development code would apply.
Warner Cook, a principal planner with Austin Planning, gave an ETOD update. The city will hold Imagine Austin open houses on Oct. 20 at Turner-Roberts Recreation Center, Oct. 21 at Dove Springs Recreation Center, Oct. 24 at Deerpark Middle School and Oct. 28 at Doss Elementary, with a virtual session Oct. 29. Cook said staff expect proposed new mixed-use zones to reach council in early 2027.
The director’s report announced CTXGO, a regional app for construction and travel information. It also reported that Austin-Bergstrom International Airport handled more than 2.1 million passengers in each of June and July.
What’s next
Ellis said the committee already has two or three items planned for November and one or two for December. No date for its next meeting was announced. Staff said the East 51st Street design moves to a final permit resubmittal in early 2027, with construction expected to begin in late 2027. Video of the meeting is on the city’s archive.